Long Thanh Airport in the final sprint to get ready for its first phase of commercial operation

Information on flight procedures, minimum operating standards and more for Long Thanh Airport has just been published, getting ready for the first phase of commercial operation.

On 16/10, the Civil Aviation Authority of Vietnam (CAAV) officially published two AIP supplements under AIRAC cycles 29/25 and 30/25, providing all the aeronautical information needed for flight operations and technical operation at Long Thanh International Airport (VVLT).

Flight procedures and minimum operating standards

Under AIRAC AIP SUP 29/25, the CAAV announced the establishment of conventional flight procedure charts, Performance-Based Navigation (PBN) procedures and Operating Minima for Long Thanh.

This dataset includes key components such as the Area Chart – ICAO, Standard Instrument Departure (SID) charts, Standard Instrument Arrival (STAR) charts, the Instrument Approach Chart – ICAO, the Visual Approach Chart – ICAO and the ATC surveillance minimum altitude chart.

Long Thanh 3
The CAAV has just published all the aeronautical information needed for flight operations and technical operation at Long Thanh International Airport (VVLT).

Notably, the SID and STAR procedures were developed simultaneously for both runways 05R and 23L, with waypoints set according to ICAO standards.

ILS, VOR/DME and RNP approach procedures are also clearly defined, ensuring compatibility with the modern navigation equipment Long Thanh is being fitted with.

Minimum operating standards for runway 05R/23L are set out specifically: for take-off, the minimum RVR is 400 m for category A and B aircraft and 500 m for categories C and D.

For landing, depending on the approach type (VOR, ILS or RNP) and lighting conditions, visibility limits range from 900 m to 3,600 m. These criteria are equivalent to those of Category I international airports worldwide.

Long Thanh 2
The passenger terminal of Long Thanh International Airport at present.

The CAAV affirmed that this set of flight procedures was established to ensure safe operations in all weather conditions, while meeting the commercial operating requirements of domestic and international airlines from the very first phase of operation.

Flight operation information for December 2025

At the same time, AIRAC AIP SUP 30/25 was published to specify the administrative, technical and operational data for the trial operation and official operation of Long Thanh International Airport in December 2025.

Accordingly, Long Thanh’s reference coordinates are 10°47’04’’N – 107°02’28’’E, about 40 km southeast of central Ho Chi Minh City, with an aerodrome elevation of 60 m above mean sea level. The 2025 magnetic variation is 1 degree West.

 

The airport has runway 05R/23L, 4,000 m long and 45 m wide, with a cement concrete surface rated PCN 76/R/A/W/T, capable of handling wide-body aircraft such as the Boeing 777, 787 and Airbus A350. Both runway ends are designed with approach lights, threshold lights, touchdown zone lights, centerline lights, sequenced flashing lights and rapid exit lights in line with ICAO standards.

Long Thanh 4
Workers on the construction site of Long Thanh International Airport in October 2025.

The main taxiways (B, B1–B12, D, D24) are 23–29 m wide with a cement concrete structure, ensuring flexible operation between the runway and the apron. The aircraft apron includes stands 6 to 9, with a cement concrete structure and load capacity equivalent to the runway. Taxiway D24 is used exclusively for entering and leaving the stands.

The rescue and firefighting system is arranged to ICAO CAT 9 standards, with 3 fire trucks, a total foam capacity of 752 liters (AFFF 3%), a discharge rate of 9,000 liters/minute, and 1 dedicated ambulance. The Long Thanh meteorological facility, in coordination with the Tan Son Nhat Aviation Meteorological Center, provides METAR, TAF and TREND reports every 6 hours, updated 24/7 for flight operations.

Synchronized infrastructure for safe, modern operation

Data in the two AIP supplements show that the CAAV has completed the key technical preparations for Long Thanh to be ready to receive its first flights from late November 2025.

Standards for the runway, signal lighting, firefighting, meteorological information, flight navigation and air traffic control are all published in ICAO format, ensuring integration with the Ho Chi Minh City area air traffic management system (Ho Chi Minh ACC) and Tan Son Nhat Airport.

These flight procedures and technical data form the basis for airlines to train flight crews and plan operations, and are the foundational documents for flight inspection, calibration and air traffic controller training before the airport officially opens.

According to the CAAV, the contents of AIRAC AIP SUP 29/25 and 30/25 will take effect from 00:00 on 27/11 and will remain in force until all data are integrated into the official AIP of Vietnam.

The simultaneous publication of AIP supplements 29/25 and 30/25 marks the final step in the CAAV’s technical preparation process.

This paves the way for the first phase of commercial operation of Long Thanh International Airport, a national key aviation infrastructure project expected to reshape the region’s air transport map.

Nam Binh – Aviation Magazine

__________________________________________

In the final sprint of the Long Thanh International Airport project, engineers and workers have completed the installation of a state-of-the-art DVOR/DME navigation system, ensuring safe and accurate flight operations for this mega airport.

On 16/10, the Vietnam Air Traffic Management Corporation (VATM) said that despite many challenges from weather and a complex construction site, Air Navigation Technical Co., Ltd. (a VATM subsidiary) had overcome all difficulties and completed the package “supply and installation of the DVOR/DME system” (an air navigation system combining two technologies) at Long Thanh International Airport on schedule, with technical quality meeting international standards.

The system provides bearing and distance information, helping pilots determine the aircraft’s exact position on the map.

This is one of the key technical items, playing a pivotal role in ensuring safe, accurate and efficient flight operations for the most modern airport in the country.

According to VATM, as the Long Thanh International Airport project is being rapidly implemented across all items, the DVOR/DME navigation system (Doppler VHF omnidirectional range and distance measuring equipment) is considered the “heart” of the navigation equipment network, helping control take-offs and landings and guide aircraft in all weather conditions.

Therefore, from the very first days of implementation, the engineers and technicians of Air Navigation Technical Co., Ltd. worked closely with the Long Thanh Project Management Board and related units to carry out construction, installation and system integration in line with technical requirements, fully complying with the standards of the International Civil Aviation Organization (ICAO).

Through scorching sunny days and long spells of rain on the vast construction site, amid the roar of machinery, engineers, workers and experts kept working tirelessly, “overcoming sun and rain” and “only discussing how to do it, never backing down”.

These simple slogans became guiding principles, giving energy to the staff, engineers and workers, helping them stay on schedule under all difficult conditions and ensuring that every installation detail met exact standards.

Installation completed of the most modern “navigation eye” system at Long Thanh Airport - Photo 2.

Installing the sideband antenna mast at component project 2 of Long Thanh Airport.

The management of Air Navigation Technical Co., Ltd. also regularly gave direct instructions on site, closely following construction developments to promptly resolve technical issues and encourage the team.

According to VATM, from 6/10 to 12/10 the company’s technical team worked with the flight inspection and calibration crew to carry out flight checks and calibration of the Long Thanh DVOR/DME equipment.

After many days of continuous work, the technical parameters were fine-tuned, and the system now operates stably, meets inspection standards and is ready to be put into service.

To date, the installation, calibration and flight inspection of the Long Thanh DVOR/DME system have been basically completed, and it is moving into the inspection, acceptance and handover stage for official operation.

This is not only an important milestone in the progress of the Long Thanh International Airport project, but also vivid proof of the effort, professionalism and high technical capability of Vietnamese engineers in air traffic management, operation and navigation.

______________________________________

Long Thanh Airport is being built on a 5,000-hectare site in Long Thanh commune, Dong Nai province, divided into 4 component projects. Component project 1, covering state management offices such as customs, police, the airport authority and quarantine, is progressing very well.

Component project 2, covering air traffic management works including the control tower, operations buildings and radar systems, is also racing toward completion.

Component project 3, with the passenger terminal, 2 runways, taxiways, aprons and connecting roads, is achieving good output and running ahead of schedule.

Component project 4, covering maintenance hangars and in-flight catering, has also broken ground simultaneously and will be completed in sync with the other items, so that Long Thanh Airport can be inaugurated on 19/12 and put into operation in the first half of 2026.

Minh Tue – Bao Xay dung

Statistics on Operating Industrial Parks in Vietnam by Region

Statistics on the number of operating industrial parks by region help investors see clearly which...

How Many Industrial Parks Are Operating in Vietnam Today?

The number of industrial parks currently operating in Vietnam is 324, out of a total...

What Is an Industrial Park? Industrial Parks vs. Industrial Clusters vs. Export Processing Zones

What is an industrial park? This is a familiar question for newcomers to industrial real...

Industrial Park Occupancy Rate 2026: What the Figures Say About Land and Factory Leasing Opportunities

The industrial park occupancy rate measures how much of the land has already been leased...

Number of Operating Industrial Parks in Vietnam: Latest Update and How to Read the Figures

The number of operating industrial parks is the first indicator investors should look at when...

How Many Industrial Parks and Export Processing Zones Does Vietnam Have? Latest Data and How to Choose a Factory Location

How many industrial parks and export processing zones does Vietnam have? Foreign investors and domestic...